Aquatic-Recreation Center Construction Schedule








Article Source:  City of San Bruno - CA


 Upcoming in October/November 2021

  • Demolition of pool building and pool
  • Demolition of gym building

 

Construction Impacts

Phase 1 - Fall 2021 to Fall 2023

  • Veterans Memorial Recreation Center is closed. Recreation Center is temporarily relocated to 618 San Mateo Avenue
  • Sidewalk access through City Park Way is closed. Pedestrians is detoured through the park

Phase 2A, 2B & 2C - Spring 2022 to Summer 2023

  • City Park Way will be intermittently closed
  • Pathways and parking space closures within construction zone. Pedestrians will still have access to pathways in the park
  • Vehicular traffic will be detoured to El Camino Real

Phase 3 - Spring 2022 to Summer 2023

  • New Parking Lot will be available Fall 2023

###