Week of July 14, 2025 work will include:
- Final inspections on Huntington Ave. work
- Final inspections on Southline Ave. work
- Demobilization of Tanforan Ave. sanitary sewer bypass
- Preemption tie-in at Dollar Ave. and S. Linden Ave. intersection
- PG&E electrical tie-in to homes on Tanforan Ave. Houses (dates TBD)
Week of July 21, 2025 work will include:
- Final inspections on Huntington Ave. work
- Final inspections on Southline Ave. work
- Demobilization of Tanforan Ave. sanitary sewer bypass
- Preemption tie-in at Dollar Ave. and S. Linden Ave. intersection
- PG&E electrical tie-in to homes on Tanforan Ave. Houses (dates TBD)
- Continued work at Dollar Ave. and S. Linden Ave. intersection
If
there are any questions or concerns regarding the work that is
occurring, please call (805) 215-2517. A member of the project team